Restoration Project Lowdown
Among the more interesting projects that either have been
completed or are underway by volunteers:
Repair of shorted and otherwise damaged electric circuits.
Only about 30% of the branch circuits worked when we began
in the Loew's. This was an extreme example of a problem many
people face in renovation work. We were fortunate in that all
of the original wiring in the Theatre is in black pipe conduit.
That meant the wiring was safe and reusable if the shorts could
be cleared. Volunteers spent months tracing circuits, removing
fixtures to look for shorts and replacing damaged sections
of wire. Today, over 95% of the Theatre's original circuits
are operational.
Tracing and repairing the Theatre's complicated network
of steam pipes and radiators. Steam systems are
rarely installed new any more, but replacing one with a modern
hydronic system as part of a renovation/restoration is often
prohibitively expensive. That means a renovator not only
has to install modern and efficient boilers and condensate
pumps, which was done in the Theatre by contractors, but
also deal with a variety of unique steam system problems
-- such as sticking traps, corroded condensate pipe and bad
pitch on pipes that can cause them to bang. In the Loew's,
a couple dozen traps were replaced, as were numerous fittings
and pipe lengths, and several sections of badly pitched pipe
were adjusted by our in-house crew.
Demolition
of non-original partition walls that were built in 1974,
which divided the auditorium into three cinemas. Like
many a homeowner restoring his house, our volunteers faced
the task of undoing poorly conceived alterations. In the
case of the Theatre, these alterations included 30-foot-high
walls made of six layers of sheet rock and double metal studs,
and filled with fiberglass insulation. The debris from this
demolition filled eight large dumpsters. One contractor estimated
the job would cost over $100,000. Volunteers did it for the
cost of Sawzall blades and soda. (more info soon)
Cutting
and partial removal of a non-original, five-inch-thick poured
concrete slab and supporting steel and brickwork. This
non-original slab blocked the center entrance to the Theatre's
auditorium. Volunteers wielded 14-inch cut-off saws and demolition
hammers to do the job. (more info soon)
Rebuilding the original poured concrete risers/footing
for seats. These had been jack-hammered out as
part of the 1974 triplexing of the auditorium. Volunteers
recreated the original shapes in new form work, and mixed
and poured new concrete.
Complete
restoration of the original projection booth. The
room had been stripped of all equipment and left open to
the elements and pigeons. It was a complete disaster, a true
renovation nightmare. A volunteer filled missing voids in
the plaster walls and ceiling, repaired cracks, skim-coated
chipped surfaces, primed and repainted. Another volunteer
completely rebuilt the room's technical capabilities, installing
a rebuilt sound system, two modern projectors plus a vintage
Vitaphone projector -- the first form of "talking" projection
equipment and identical to the projectors the Theatre was
equipped with when it opened. The room is now one of the
best-equipped projection booths in New Jersey. (more info
soon)
Continue => |